Excavation of Naperi School Water Channel Trench, Machine Based


Construction to a water way to block flash floods from affecting Naperi School

Protection of people and school infrastructure

Start date: 2021-09-20 Due date: 2021-11-20 Approval date: 2021-09-13
Climate Financed
Orange Category (7 Red Flags)
Lack of supporting feasibility study Lack of environmental impact assessment Lack of social Impact assessment Lack of cost benefit analysis Public consultation meetings not held Limited competition Lack of maintenance plans
6,750,025.00   MWK
Total Budget
2023-04-20
Date Created
2025-12-04
Last updated
Construction
Project Type
Completion
Project Status

Locations

Description Naperi School in TA Amidu
District Balaka
Region Southern
Street address
Postal code

Documents

No records were added

Parties

No records were added

Contracts

OCID BDC/RFQ/DISASTER/2020-21
External Reference
Title Excavation of Naperi School Water Channel Trench, Machine Based
Description Completed
Status Closed
Contract Value MWK 6,750,025.00
Cost Estimate MWK 6,750,025.00
Final Value 0.00
Start Date 2021-09-20
End Date 2021-10-20
Max Extent Date 2021-11-20
Duration In Days 61
Procurement Method Selective
Method Details Best value to government
Procuring Entity Balaka District Council-Balaka-MW
Administrative Balaka District Council-Balaka-MW

Documents

No records were added

Modifications

No records were added

Budget

No records were added

Project Funding

Party Malawi Government-Lilongwe-MW
Amount MWK 6,750,025.00
Description Under Department of Disaster
No comments added

Environment

No record was added

Completion

End Date: 2021-10-20
End Details:
Final Scope:
Final Scope Details:
Final Value Amount: MWK 6,750,025.00
Final Value Details:

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines

Asset Life Time

Start Date 2021-10-20
End Date 2023-10-20
Max End Date 2024-10-20

© 2026, Construction Sector Transparency Initiative (CoST Malawi). All Right Reserved;

All content on the platform is licensed under Creative Commons Attribution 4.0 Unported License.