image

Construction of Dzunje Maternity Wing


The project will involves construction of Block, sanitary fittings, waste & sanitary installations, Water installations, Firefighting installations, solar installation and electrical installation.

The project will promote safe motherhood and reduce maternal and neonatal death

Start date: 2022-01-10 Due date: 2022-04-10 Approval date: 2022-01-03
Climate Financed
Orange Category (8 Red Flags)
Lack of supporting feasibility study Lack of environmental impact assessment Lack of social Impact assessment Lack of cost benefit analysis Public consultation meetings not held Limited competition Project delays Lack of maintenance plans
52,219,999.00   MWK
Total Budget
2023-05-17
Date Created
2025-12-04
Last updated
Construction
Project Type
Implementation
Project Status

Locations

Description TA Kwataine, Central Constituency, Dzunje Ward, Lipenga VDC
District Ntcheu
Region Central
Street address
Postal code

Documents

Title Contract of Dzunje Maternity Wing
Description Dzunje Maternity Wing Contract
Document Type Contract summary
Date Published
Date Modified
Language
Page Start
Page End
Author
Access Details
Title Contract of Dzunje Maternity Wing Revised
Description Dzunje Maternity Wing revised contract
Document Type Contract summary
Date Published
Date Modified
Language
Page Start
Page End
Author
Access Details

Parties

Description Ntcheu District Council
Locality Ntcheu Boma
Region Central
Street address Ntcheu
Postal code 0000
Country Malawi
Telephone 09000000000
Fax Number
URL
Roles Payer
Description

Contracts

OCID 091/NUDC/GESD/WORKS/DZUNJE MATERNITY WING/21/22FY/03
External Reference
Title Contract of Dzunje Maternity Wing Revised
Description Contract of Dzunje Maternity Wing
Status Active
Contract Value MWK 52,221,999.00
Cost Estimate MWK 43,219,999.00
Final Value 0.00
Start Date 2022-01-10
End Date 2022-04-10
Max Extent Date 2023-12-21
Duration In Days 710
Procurement Method Open
Method Details Lowest cost
Procuring Entity Ntcheu District Council-Ntcheu Boma-MW
Administrative Ntcheu District Council-Ntcheu-MW

Documents

No records were added

Modifications

No records were added
OCID 091/NUDC/GESD/WORKS/DZUNJE MATERNITY WING/21/22FY/03
External Reference
Title Contract of Dzunje Maternity Wing Revised
Description Contract of Dzunje Maternity Wing
Status Active
Contract Value MWK 52,221,999.00
Cost Estimate MWK 43,219,999.00
Final Value 0.00
Start Date 2022-01-10
End Date 2022-04-10
Max Extent Date 2023-12-21
Duration In Days 710
Procurement Method Open
Method Details Lowest cost
Procuring Entity Ntcheu District Council-Ntcheu Boma-MW
Administrative Ntcheu District Council-Ntcheu-MW

Documents

No records were added

Modifications

No records were added

Budget

Description Dzunje budget
Amount MWK 52,219,999.00
Start Date 2022-01-10
End Date 2022-05-10
Max Extent Date 2023-12-21
Duration In Days 710
Party ID Ntcheu District Council-Ntcheu-MW
URI

Project Funding

Party World Bank-Washington, DC-US
Amount MWK 52,219,999.00
Description GESD funded project
No comments added

Environment

No record was added

Completion

End Date:
End Details:
Final Scope:
Final Scope Details:
Final Value Amount: 0.00
Final Value Details:

Finances

No records were added

Milestones

No records were added

Transactions

No records were added

Benefits

No records were added

Additional Classifications

No records were added

Social

No records were added

Metrics & Forecasts

No records were added

Policy

No record was added

Timelines

© 2026, Construction Sector Transparency Initiative (CoST Malawi). All Right Reserved;

All content on the platform is licensed under Creative Commons Attribution 4.0 Unported License.